(1) The Setback violations against the approved plan but within the provisions of Zoning Regulations or Building Byelaws or Transfer of Development Rights (TDR) rules may be regularised on payment of difference of prescribed fee under section 18 of the Act.
(2) Setback violations shall be calculated based on the percentage deviations made on each side against approved plan or as prescribed in the Zonal Regulations.
(3) The setback violations shall be calculated except open Chajja or Balcony. Buildings constructed by violating the road widening line (mentioned as building line in certain Zoning Regulations) shall not be considered for regularisation, unless the portion of the building projected beyond the road widening line is demolished.