(1) This Act may be called the Karnataka Industries (Facilitation) (Amendment) Act, 2020.
(2) It shall be deemed to have come into force with effect from 2nd day of July, 2020.
In the Karnataka Industries (Facilitation) Act, 2002 (Karnataka Act 45 of 2003) (hereinafter referred to as the principal Act) in section 2,-
(i) In clause (ia), the following shall be inserted at the end, namely:-
“the Legal Metrology Act, 2009 (Central Act 1 of 2010) or rules made there under, the Karnataka Municipalities Act, 1964 (Karnataka Act 22 of 1964), the Karnataka Municipal Corporations Act, 1976 (Karnataka Act 14 of 1977), the Karnataka Grama Swaraj and Panchayat Raj Act, 1993 (Karnataka Act 14 of 1993), the Karnataka Industrial Area Development Act, 1966 (Karnataka Act 18 of 1966), the Karnataka Fire Force Act, 1964 (Karnataka Act 42 of 1964), the Karnataka preservation of Trees Act, 1976 (Karnataka Act 76 of 1976), the Karnataka Forest Rules, 1969, the Karnataka Land Revenue Act, 1964 (Karnataka Act 12 of 1964), the Karnataka Land Reforms Act, 1961 (Karnataka Act 10 of 1962), the Bangalore Development Authority Act, 1976 (Karnataka Act 12 of 1976), the Karnataka Urban Development Authorities Act, 1987 (Karnataka Act 34 of 1987), the Karnataka Town and Country Planning Act, 1961 (Karnataka Act 11 of 1963), and the policies of the Karnataka State Small scale Industries Development Corporation.”
(ii) after clause (vii), the following shall be inserted, namely:-
“(vii-a) “Manufacturing Enterprise” means the enterprise engaged in the manufacture or production of goods pertaining to any industry specified in the first schedule to the Industries (Development and Regulation) Act, 1951 or employing plant and machinery in the process of value addition to the final product having a distinct name or character or use.
(vii-b) “Manufacturing industry” means the industry which involves in the manufacturing and processing of items and indulges in either creation of new commodities or in value addition.”
In section 13 of the principal Act,
(i) in sub-section (1), after clause (g), the following shall be inserted, namely:-
“(h) on receipt of combined application form from the manufacturing industries or enterprises, the respective nodal agency shall issue an acknowledgment certificate, after obtaining the approval by the investment committees, namely State High Level Clearance Committee, State Level Single Window Clearance Committee or District Level Single Window Clearance Committee, in the prescribed form, to the applicant:
Provided that, land shall be considered for the purpose for which it is being acquired or permission for which it is applied for.”
(ii) after sub-section (2), the following shall be inserted, namely:-
“(3) In respect of manufacturing industry or manufacturing enterprise, the acknowledgement certificate issued under clause (h) of sub-section (1) shall deemed to be the clearances for setting up or establishment of Industry as defined in sub-section (iii) of section 2, granted or issued by the respective departments for an initial period of three years or till the date of commencement of commercial operations, whichever is earlier, from the date of its acknowledgement:
Provided that, such deemed clearance for setting up of Industry shall be only to the Land for the purpose for which it is being acquired or permission is applied for. Further, there shall not be any deviation in construction with reference to the building bye-law and to the land use specified in any applicable Act or the master plan, wherever such plan is in force.
Provided further that, the approvals shall not entitle the manufacturing industry or manufacturing enterprise to use a land without clear title or lands falling under dispute, restricted categories etc.,. The ceiling limit of area that can be acquired or utilized under the provisions of this Act shall be limited as per the provisions under section 109 of the Karnataka Land Reforms Act, 1961(Karnataka Act 10 of 1962).
Explanation: Where the manufacturing industry or manufacturing enterprise establishes as per sub-section (3), the applicant has to take necessary clearances as per sub-sections (2) and (3) of section 14, before commencement of commercial operation.
(4) To assist various administrative or line departments whose powers are devolved upon the nodal agency under various legislations, Acts, rules or regulations for obtaining the approvals and monitoring the implementation of the project.
(5) To monitor and maintain the record of the applications or proposals and acknowledgement certificate issued.
(6) The state level nodal agency to maintain the database of all the project applications, approvals or acknowledgements as a central repository through the online systems.
Explanation: List of services, approvals or clearances that are required to be brought under the purview of acknowledgement certificate shall be considered as clearances by the departments for an initial period of three years or till the date of commencement of commercial operation, whichever is earlier for manufacturing industry or manufacturing enterprise. The list of the services, approvals or clearances shall include clearances as defined in clause (iii) of section 2.