Form –Vi (See Regulation 9(1)) Sanction Of Single Plot For Development Of Building
Sub: Sanction of Single plot for....................purpose in plot(s) bearing Sy.No (s).............of.............. Village............... Hobli................ Taluk to carry out development of Building .
Ref: 1.Application dated..
-
Receipt of fee under regulation 8(6) for Rs........... (Receipt No......... Dated.........)
-
Technical approval of Single plot for demarcation Order No: ………. dated…….
-
Intimation from the applicant regarding demarcation of the Single plot in letter No............. Dated..
-
Technical approval of Single plot for development Order No: ………. dated…….
On receipt of the application cited in reference (1) above, the application has been verified and the stipulated fee under regulation 8(6) has been collected from the applicant vide receipt under reference-(2). The Sanction of Technical approval for Single plot for.... ....purpose in plot(s) bearing Sy.No(s) of Village Hobli Taluk under regulation 9(1) of the Karnataka Town and
3325
Country Planning ( Development of Land in areas other than Local Planning Areas ) Regulations, 2025 was accorded to demarcate and set-it-out on ground in letter cited in reference (3 ) above.
The applicant has demarcated and set on ground the Single plot/Subdivision/Layout Plan and has fixed the specified markers and painted and intimated the same in the letter under reference-(4).
The Director/ Addl director/Joint Director/Assistant Director has inspected and verified the demarcated single plot and accorded technical approval for the Single plot in Form-V under reference(5) to accord Sanction of the single plot and release the building site for development
Hence Sanction of Single plot for. .purpose in plot(s) bearing Sy.No(s)…… ..of... ...Village...............Hobli...Taluk under regulation 9(1)(i) (a) is hereby accorded and the building site is released for development subject to the following conditions, viz.-
(1) The Residential / Non residential Building site, as the case may be, sanctioned finally under this order is fit for sale/ registration;
| Type | Dimension of building site | Extent of building site in Sqm | Schedule | |||
| North | South | East | West | |||
| 1.Residential/Non-residential Building | ||||||
(2)... ......(such other conditions)
Three (3) Copies of the approved Single plot are hereby enclosed for reference. Jurisdictional Chief Officer/PDO of the Local Authority.
Office Seal
To,
The Applicant, Address..
Copy, with a plan for information.-
Director/ Addl director/Joint Director/Assistant Director
ಭಾ ಗ 4J
Sub: Sanction of Provisional Single plot/ layout/Sub-division Plan for....................purpose in plot(s) bearing Sy.No (s).............of.... Village............... Hobli................ Taluk, to carry out development works.
Ref: 1.Application dated...... 2. Technical approval of Single plot/layout/Subdivision plan for demarcation Order No: ………. dated……. 7 1-
-
Application dated..
-
Technical approval of Single plot/ layout/Sub-division Plan for Development purpose in Form-V On receipt of the application cited in reference (1) above, The Sanction of Technical approval for Single plot/ Layout Plan /Sub-division for... ....purpose in plot(s) bearing
Sy.No(s).............of..............Village........ ...Hobli… .Taluk under regulation 9(1) of the Karnataka Town and Country Planning ( Development of Land in areas other than Local Planning Areas ) Regulations,2025 was accorded to demarcate and set-it-out on ground in letter cited in reference (2) above.
The Director/ Addl director/Joint Director/Assistant Director has accorded technical approval for the Single plot/Layout Plan/ Sub-division in Form-V under reference (4) to accord provisional Sanction of the Single plot/ layout/Sub-division Plan to take up development works.
The applicant now in letter cited in reference (3) above, has submitted the Registered relinquishment deed, wherein the applicant has relinquished the areas under Roads/Streets, Parks, Public Utility areas, Vehicle Parking, any other infrastructure facility (as the case may be) Civic amenity areas to the Local Authority through registered relinquishment deed free of cost without claiming any compensation and has executed the registered mortgage deed of all the corner sites and un release intermediate sites in the layout to the local authority.
Hence Sanction of Provisional Single plot/ Layout/Sub-division plan for... .......purpose in plot(s) bearing
3327
Sy.No(s).............of..............Village...............Hobli .............Taluk under regulation 9(2) is hereby accorded to carry out development works subject to the following conditions, viz.-
(1) sanctioned provisional single plot/layout/subdivision plan as set-out on ground is hereby issued for carrying out development works and shall be developed as specified under these regulations;
(2) The Landuse Analysis of the layout / subdivision Plan is as shown below.
| Sl.no | Landuse | Area in sqm | Percentage |
| 1 | Residential/commercial | ||
| 2 | Parks and open spaces | ||
| 3 | Civic amenities | ||
| 4 | parking | ||
| 5 | Utilities <sub>In</sub> | ||
| 6 | Roads | ||
| Total |
(3) Building sites or any part of the layout/sub-division plan sanctioned provisionally to carry out development works except 40 percent sites released herewith, is not fit for allotment or sale or registration;
| Type | Dimension in metre | Building Site numbers | Total number s |
| 1. Residential Building Sites | |||
| 2.Non-residential Building Sites | |||
| a. Commercial | |||
| b. Industrial | |||
| Total |
ಭಾ ಗ 4J
(4) Specified markers fixed and depicting the Residential and Non-Residential Building Sites shall not be altered without prior approval from the Director or his sub ordinate officer as the case may be;
(5) On completion of all development works and obtaining the completion certificate from the Concerned Authority or Agency or Department including the development of parks and civic amenity sites the applicant shall submit an application for final sanction of layout/sub-division plan within the time limit specified under the Karnataka Town and Country Planning ( Development of Land in areas other than Local Planning Areas) Regulations,2025
(6) ...(such other conditions)
Three (3) Copies of the technically approved Single plot/ layout/ sub-division plan are hereby enclosed for reference.
Jurisdictional Chief Officer/PDO of the Local Authority.
Office Seal
To,
The Applicant, Address..
Copy, with a plan for necessary action with regard to development works, to:
-
Jurisdictional officer of Panchayatraj Engineering Department for civil works (wherever plot(s) falls in Gram Panchayat limits).
-
Jurisdictional officer of BWSSB/KUWSSB/Panchayatraj Water supply and Sanitation Department for water supply and underground drainage works.
-
Jurisdictional officer of ESCOM’S for electrification work.
-
Jurisdictional officer ofKSPCB for issue of CFE and CFO wherever applicable.
Copy, with a plan for information.-
Director/ Addl director/Joint Director/Assistant Director
3329