(1) Every application for grant of permission for an advertisement shall be made to the Chief Commissioner in Form-III.
(2) Every application made under sub-rule (1) shall contain,
(i) a plan of the advertisement to be erected indicating the height and other dimensions and the material proposed to be used as approved by a qualified engineer;
(ii) a no objection certificate from the owner of the land where the advertisement is to be erected in a private land or building or a no objection certificate from the State or Central Government Department concerned, if the advertisement is to be erected on the land of State or Central Government or a no objection certificate from the Chief Commissioner of the BBMP if the advertisement is to be erected on BBMP land:
Provided that, in respect of State and Central Government land, the no objection certificate shall be issued by an Officer not lower in rank than that of an Assistant Executive Engineer as the case may be;
(iii) a topographical sketch indicating the proposed location of the advertisement.
(iv) Structural Stability certificate as well as the Occupancy certificate of the building (wherever obtaining an occupancy certificate for such building is mandatory),in case of the advertisement proposed for being erected on any existing building. But if such a building does not have the Occupancy Certificate, then the fees shall be calculated as in sub-rule (3)
(b) and the owner of the building shall provide an undertaking in Form-XI.
(3) Fee:
(a) Every application made under sub-rule (1) shall be accompanied by a Challan for payment of the Application fee specified in the Schedule-I.
(b) In case of the advertisement proposed for being erected on any existing building without the Occupancy Certificate, 150% of the fees calculated as per the fee specified in the Schedule-I and any other penalty that may be decided to be levied by the government on buildings which are unauthorised or deviate from sanctioned plan shall be paid.
(4) The Chief Commissioner shall, after satisfying himself that the applicant has complied with all the requirements of the Act and rules, before issuing the permission for erection and display of hoarding, shall raise a Demand in Form-V for the Advertisement Fee as specified in Schedule–I. This demand shall be complied with by the Applicant (Licensed Agency) within a period of 15 days.
Once the Advertisement Fee has been paid in full by the Applicant, Chief Commissioner shall grant the permission in Form-VI for erection of hoarding within a period of 7 working days from the date of payment of such Advertisement Fee.
(5) The permission granted under this rule shall be valid for not more than three years.
(6) Applicant can appeal against decisions taken by the Chief Commissioner with the Advertisement Regulatory Committee Constituted under these rules.
(7) Change of location of display including Legacy may be allowed once, against an application and payment of requisite fee, provided the new location is in line with the provisions of these rules.
(8) Transfer of Permission for a hoarding/billboard from one Agency to another shall be allowed against the submission of NOC to such transfer from the Agency presently holding such permission and one time payment of Rs.10,000/-. The Agency acquiring the Permission shall intimate the Chief Commissioner in Form IV-A along with a Demand Draft for requisite amount. Under such transfer, the Agency acquiring the Permission shall be deemed to have obtained the assets and liabilities of the related billboard from the date of intimation to the Chief Commissioner as above.